Progress This Season on Contracts Involving $6,000,000.
|
|
ALBANY, Sept. 9. — The State Canal Board has finished plans for work on the 1,000-ton barge canal during the coming season. State Engineer Van Alstyne, from reports to date on the six contracts already let, said that work was well under way on contracts 1, 2, 3, and 6, and that the plants for work on contracts 4 and 5 had been set up. |